01/25/03 - *** Video One *** Video Two ***
01/25/03 - Cleared lot (more pictures coming)
02/05/03 - Footings dug/footing forms/footing rebar
02/11/03 - Rebar footings pinned/retaining wall footing dug and rebar/temp. power
02/12/03 Noon - Rebar pinnings finished/retaining wall footing poured
02/12/03 Night - Basement wall forms set up
02/13/03 - Retaining wall, wall forms/walls poured
02/22/03 - Basement waterproofing & drainage/install sewer line
02/28/03 - Garage bays filled in/landscaping to basement walls
03/05/03 - Gravel basement & garage/vapor barrier/basement & garage forms
03/08/03 - Garage & basement poured/floor trusses & ceiling joists delivered
03/10/03 - Framing begins for basement and 1st floor subfloor
03/11/03 Noon - Tubs delivered/1st floor framing
03/11/03 Night - Garage framing/2nd floor subfloor
03/13/03 - Roof Framing/basement staircase installed
03/14/03 - Plywood exterior/fireplace framing/main staircase installed
03/15/03 - Roof tar paper/windows delivered/shingles delivered
03/15/03 - *** Video One *** Video Two *** Video Three *** Video Four ***
03/17/03 Noon - Hot & cold water pipes/drain plumbing/tub & shower install/shingles installed
03/17/03 Night - Windows installed/exterior doors installed
03/19/03 - HVAC/electrical/deck/fireplace/circuit breaker
03/28/03 - Siding & shutters installed/insulation
03/31/03 - Insulation sealed/sheetrocking
04/01/03 - Sheetrocking completed
04/03/03 - Sidewalk & driveway poured/sewer line connect/tape and mudding of sheetrock
04/10/03 - Window sills/door & window moulding/popcorn ceiling/FP mantle & marble
04/11/03 - Stone install begins on garage front
04/15/03 - Garage door installed/cabinets & countertops arrive/rail install & stain
04/17/03 - Cabinets & countertops installed/front stoop install begins
04/24/03 - Mailbox/2nd garage door/closet shelving/carpet padding/carpeting/closet doors
05/03/03 - Redo front steps into porch